Skip to content

Bid Opportunities

Tug Public Post (2)

Barge Operations (November 2026):

  • 100’ x 60’ spud barge to support five cable landings and protection in Lake Superior, barge will also be used as dive platform
  • Tug to support barge movements
  • Dive team to install 200m of articulated pipe protection on cables, articulated pipe segments are cast iron (0.5m length = 20kg weight)
  • Dive team to include surface supplied air and communications
  • Operating depths = 0 to 20m
  • ~2 weeks of operations

Tug Operations (November 2026):

  • Tug to support cable landing operations and to be used as dive platform in Lake Superior
  • Divers to support landing cable at beach and provide cable management on seabed
  • Five cables to be landed, 2-3 days apart, cables will be bundled together after each landing
  • Dive team to manage cables on lakebed and bundle cables together following landing
  • Dive team to include surface supplied air and communications
  • Operating depths = 0 to 20m
  • ~15 days of operations

To express interest and receive the bid forms and specifications contact Sandra A Sherlock ssherlock@whoi.edu please respond by September 25th 2026 to obtain the information. WHOI is not obligated and will not pay for any information received from potential offerors as a result of this announcement.