Woods Hole Oceanographic Institution
Cruise Planning Questionnaire
ALVIN Certification Cruise (ACC)
Ship
R/V AtlantisVehicles
HOV AlvinCruise Party
J. Patrick Hickey: Chief Scientist, Principal InvestigatorWoods Hole Oceanographic Institution Smith 301, MS#17 Woods Hole, Ma. USA 02543
+1 508 289 3860
jhickey@whoi.edu
Departure: Woods Hole on Apr 1, 2013
Arrival: St. Georges Bermuda on May 1, 2013
Mobilization Date: Mar 18, 2013
Demobilization Date: May 3, 2013
Supporting documentation:
Operations Area: Off Bermuda
Lat/Lon:
Depth Range: min / max (m)
Will the vessel be operating within 200 NM of a foreign country? Bermuda
Are visas or special travel documents required? no
Science objectives
HOV ALVIN Sea trials for post overhaul Alvin upgrade.Science Activities
Launch and Recover of HOV ALVIN as determined by Ch Sci.Pre-cruise planning meeting: Teleconference/Visit WHOI
Stations:
Funding Agency: NSF #0000001
- added NSF #0000001 on Jan 9, 2013 3:21 PM by Eric Benway
R/V Atlantis
Shipboard Equipment
Bathymetry System 12 kHzBathymetry System 3.5 kHz
Shipboard Communication
Basic Internet access via HiSeasNetIs there a need to receive data from shore on a regular basis?
CTD/Water Sampling
911+ Rosette 24-position, 10-liter bottle Rosette with dual T/C sensorsCritical CTD Sensors:
Storage Notes:
Navigation
Will you be using Long Base Line (LBL) navigation? no
Will you be using Ultra-short baseline (USBL) navigation for other than Alvin operations? no
Navigation Notes:
Winches
CTD Winch with .322" Electro-mechanical wireWinch Notes:
Wire Notes:
| Slip ring required? no | Number of conductors: |
| Non-standard wire required? no | Type: |
| Traction winch required? no | Describe: |
Other Science Vans:
Specialized Deck Equipment
| Mooring Deployment/Recovery Equipment Required: no | Type: |
| Cruise Specific Science Winch Required: no | Type: |
| Nets Required: no | Type: |
Over the Side Equipment
Will you be bringing any equipment (winches, blocks, etc.) that lowers instruments over the side? noSpecial Requirements
| Elecrical Power: no | Identify: |
| Equipment Handling: no | Identify: |
| Inter/intraship Communications: no | Identify: |
| Science Stowage: no | Identify: |
| Water: no | Identify: |
Additional Cruise Items/Activities
| Explosive Devices: no Portable Air Compressors: no Flammable Gases: no |
Small Boat Operations: yes SCUBA Diving Operations: no |
Hazardous Material
Will hazardous material be utilized? no
Radioactive Material
Radioiosotopes: noAdditional Information
Is night time work anticipated on this cruise? no
Specialized tech support (Seabeam, coring, other):
Other required equipment and special needs:
HOV Alvin
Site Survey
Will you provide detailed charts of the work area(s)? noCurrent Chart(s):
If no, willl you need R/V Atlantis to generate maps of the work area(s)? no
Will you need post-dive maps of the work area generated? no
Navigation
Will you be using Long Base Line (LBL) navigation? no
Will you be using Ultra-short baseline (USBL) navigation for other than Alvin operations? no
Vehicle Equipment
CTDSearch sonar
What type of samples do you expect to collect?
Elevators
Will you be using elevators to transport samples to the surface? no
If yes, how many would you anticipate?
Science Supplied Equipment
Are you supplying equipment to be used on HOV Alvin? no
Has this equipment been used on Alvin before? no
Please give a brief description of the equipment, its intended purpose, the cruise # it was last used on if any and its deployment method.
Does this equipment use an external pressure housing? no
Has the pressure housing been tested per Alvin Pressure Test requirements? no
Does the equipment have an associated computer or control panel for remote operation from the personnel sphere? no
Has the computer or control panel been gas tested for use in the personnel sphere? no
Air weight of this equipment?
Does the equipment require data or a power interface from the vehicle? no
Does the equipment meet the electrical requirements of the Alvin User Manual? no
Wiring diagram required for this equipment.
Does this equipment require hydraulic inputs from the vehicle? no
Hydraulic schematic of the equipment requirements.
Does this equipment require manipulation? no
If yes, please describe how the equipment is to be manipulated: HOV testing only
Will this equipment be deployed off the vehicle? no
If yes, please describe how the equipment is intended for deployment: HOV testing only
If yes, will the equipment be disconnected from the vehicle and left in situ? no
How long will the deployment be?
Will the equipment be recovered by the same vehicle? no
Do you intend to recover any other previously deployed equipment? no
If yes, please describe this equipment:
Does this equipment use any glass spheres for either buoyancy or as pressure housings? no
Hazardous Material
Will hazardous material be utilized? no
Additional Information
Brief operations description or comments:Date Submitted: Jan 9, 2013 3:24 PM by Eric Benway